June 8th 
Attendees: Eric, Derek, Sarah, Laura, Aaron, Brian, Sid, and Nathan

Contractor update: recommendation to upgrade sewer lines and grease trap on east side of existing building

Architect update: sidewalk placement around new classrooms and gym; next meeting will be choosing styles and colors of carpet, etc.; need to get input from PreK and K teachers about number of tack boards and white boards; power door options; revised concessions layout; scoreboard placement and kind of scoreboard in new gym

Engineering update: camera placements in gym and weight room

Update to Action deadlines: Site Plans release- June 20th; Construction Documents release- June 28; Site Prep by Wiens- July 5; date- July 18 (could change); Contracts decided on at Special BOE meeting- July 31st; Construction start- August 14 (possibly earlier); Classroom complete- May 15, 2018; Gym addition complete- June 15, 2018


Next meeting: June 15th at 1 pm in district office
Posted by nathan.reed On 14 June, 2017 at 9:05 AM  2 Comments

Comments
essaymama review (Guest) said On 26 April, 2018 at 2:38 AM
Such an amazing recording of the radio show. I listen this complete audio. I recommend you all download and listen this audio to entertain yourself. Keep sharing this audio,  
asdf (Guest) said On 31 March, 2018 at 3:28 AM
scoreboard placement and kind of scoreboard in new gym   
Leave Your Comment
Security Measure