May 17, 2017  
Present: Sid, Sarah, Laura, Derek, Eric, Aaron, Brian, and Nathan

Sid presented:
Geotechnical Study should be concluded by 5/22/17
Site Survey still has not been submitted- a copy will be shared with district and design team ASAP
HVAC at gym and weight room area recommendations- 4 total units

Sarah presented:
Classroom drawings review and discussion- 65-70% complete
Gym schematic plan and discussion
-decision made to make the weight room area the storm shelter for better access of patrons and students as well as city of Langdon
- may need to add a few columns in weight room to support deck above
The AD and coaches had input on locker room/ coach office/ and storage space for PE
- Decision to make the janitor room the new women's restroom entrance in the commons bathroom, this will allow to use add access control doors near band room hallway

Laura (Engineer) shared recommendations:
- go with a natural gas generator, district reps agreed
- classroom electrical discussion, where to put plug-ins and which lights to add dimmers to
- intercom and clock locations in new rooms

District info:
- intercom and clocks work will start in June
- access and camera budgets are pending


NEXT MEETING: Tuesday, May 30th, 2017 at 9 am in Superintendent's office

 
Posted by nathan.reed On 19 May, 2017 at 8:23 AM  3 Comments

Comments
essayservices discounts (Guest) said On 07 May, 2018 at 3:23 AM
More submitting the better services always, schematic drawings and developing the room area weight room as well. The district shared with the more concluded recommendations for new inventions.   
sdfsd (Guest) said On 03 May, 2018 at 2:42 AM
dsdgd  
jack (Guest) said On 31 March, 2018 at 3:28 AM
may need to add a few columns in weight room to support deck above  
Leave Your Comment
Security Measure